Civil Engineering

Civil Engineering Basic Field Knowledge

Civil Engineering Basic Field Knowledge

Civil Engineering Basic Field Knowledge

Important Points for The Civil Site Engineers

In the construction civil engineers doing many activities and facing quick site construction problems for solution of this problem the civil engineers must remember these points, tips & the tricks. There are general tips, tricks & tables for the civil engineers to remember it and make the construction work easier. If the quality of the construction is good. The important and basic field knowledge for civil engineers are given below. Civil Engineering Basic Field Knowledge

Civil Engineering Basic Field Knowledge

Basic Points for the Civil Engineer

The basic Field knowledge and important points for the civil engineer is given below

  1. Minimum thickness of the slab must not be less than 125 mm.
  2. For the normal construction the size of coarse aggregate ranges from ten to 20 mm.
  3. Lapping of the bar must not be used having diameter more than thirty Six mm.
  4. The height of the floor to floor should not be less than three m and not more than Four m.
  5. Water absorption of the bricks should be less than fifteen %
  6. The combination of the cement, sand & coarse aggregate should be according to design.
  7. PH value of the water should not be less than Six because below the PH value of Six it is acidic.
  8. For calculation of the unit weight of steel, the formula is D 2/162.162 in Kg/m. this formula is used when the dia of the bar is in mm. while for lb/ft the formula is used D 2/52.9 where dia of the steel is in sootar.
  9. The Concrete cover should be sufficient
  10. The compressive strength of the brick is 3.5N/mm.
  11. The Concrete should not be fall from more than 1.5 m height.
  12. Don’t use over vibrator in the concrete.
  13. For dowel bars the dia of the steel should not be less than twelve mm.
  14. For chair bar the dia of the steel should not be less than twelve mm
  15. Formwork should be tight.
  16. The longitudinal bars should not be less 0.8 % & not more than Six % of gross c/s.
  17. The minimum number of the bars in circular column is Six No’s. while in square column the number of the bars is Four No’s.
  18. Cement should be stored in the dry place. It would be raised from the Eight inches above floor level & 1 (One) foot or 300 mm away from each side of the walls. The cement bags should be stocked more than Ten bags in such a manner.
  19. The Electrical conduits shall not run in the column or beam.
  20. In the steel construction the binding wire required is Eight Kg per MT.
  21. The spacing between chair bars should not be more than One meter or 1 chair bar per One m2
  22. The dimension tolerance for cubes +, – Two mm.
  23. Earth quick excavation for the basement above Three m should be steeped form
  24. Water cement ratio must be check.
  25. Water cement ratio is the different for different grade of the concrete for example water cement ratio should be 0.45 for M20, M25 & above. 0.50 for M15, M10 and below.
  26. The cube test should be done for every thirty cubic meter (m3) area.
  27. The aggregate which are used in the concrete must be free from silt, dust & clay or other impurities.
  28. In the aggregate the angular shape is good for the construction. In angular shape aggregates it makes the bond perfect & concrete is prepared from it very strong and have high strength.
  29. In the soil filling as per IS code for every hundred square meter (m2) three sample for core cutting test should be taken.
  30. The compaction of the concrete should be done properly.
  31. Concrete should be transport to shortest route.
  32. Reinforcement design should be done according to as per IS codes.

Learn More 

How to Calculate the Bricks and Blocks in the Wall

Density of the Materials

Materials have not same density. The density is different for the different materials density of materials is given below:

S. No

Materials

Density in Kg / m3

1water1000
2cement1440
3Plain cement Concrete2400
4Reinforcement concrete2500
5Asphalt721
6lime640
7Lime mortar1760
8iron7850
9steel7850
10Aluminum2739
11Glass2580
12Zinc7135
13Lead11340
14Tin7280
15Nickle8908
16Copper8940
17Magnesium1738
18Stainless steel8000
19Igneous rock2700
20Sedimentary rock2600
21Metamorphic rock2700
22Sandstone2000
23Bricks1500 – 1800
24Clay soil1900
25Bamboo350
26Aspen420
27Ash (black )540
28Ash ( white)670
29Sandy soil1800
30Pine500

Concrete Cover or Clear Cover to the Reinforcement Bar

The Concrete cover is used to protect the rebar against corrosion & to provide resistance against fire. The thickness of the concrete is various in different members of the structure. The chart or table for the concrete cover to reinforcement bar is given.

S. No

Member of the structure

Concrete cover in (mm)

1Beam25
2Slab15
3Stair case15
4Column40
5Raft foundation Sides75
6Footing75
7Raft foundation bottom75
8Water retaining structures25
9Shear wall25
10Flat slab20
11Grade slab20
12Raft foundation top50
13Strap beam50

Curing Method of the Concrete.

The curing method of the concrete is given below

  1. spraying
  2. ponding
  3. steam curing
  4. wet covering
  5. curing chemicals

Cube Samples for the Different Quantity of the Concrete Volume.

The Cube sample is used to find the compressive strength of the concrete u should find different number of samples for different volume of the concrete. The cube samples for different qty of the concrete volume is follow.

S. No

Volume of Concrete

Number of the samples

11 to 5 m3one sample
26 to 15 m3two samples
316 to 30 m3three samples
430 to 50 m3four samples
550 plus or above 50 m3five samples

 

Removal of the Formwork or De Shuttering Time.

There are different members of the formwork such as foundation, beam, column & slabs etc. after poring of the concrete the shuttering should be remove after some time the time of de shuttering is given below.

S. No

Members of structure

Days

1Sides of the foundation, beam, columns and wallsTwo days
2Sides of the slab under 4.5 meter spanSeven days
3Sides of the slab above 4.5 meter spanForten days
4Side of the beams and arches up to Six meter spanForten days
5Side of the beams between Six meter to 9 meter spanTwenty One days
6Side of the beams and arches above Nine metTwenty Eight days

 

Weight of the Steel Bar per M/Kg

The weight of the steel bar in meter per kilogram is given in table below.

S. No

Dia of bar in (mm)

Weight of steel in Kg per meter

1Six0.22
2Eight0.39
3Ten0.61
4Twelve0.88
5Sixteen1.57
6Twenty2.46
7Twenty Five3.85
8Thirty Five6.31
9Forty9.86

Note:

The formula of used in this table is D2/162.162 in Kg/m. this formula is used when the dia of the bar is in mm and length of the bar in meter.

Conversion of the Units.

The conversion of the units is used by every civil engineers on site to make calculation good and quickly. The conversion of units is given below:

One secra = 100 ft3One pole = 1 perch
One foot = 12 inchesOne yard = 3 ft
One foot = 0.304 meterOne yard = 36 inches
One foot = 304.8 mmOne yard = 0.914 meter
One foot = 30 cmOne yard = 91.44 centimeter
One mile = 1.609 kmOne yard = 9144 millimeter
One millimeter = 0.039 inchOne karam 5.5 ft
One inch = 25.4 mmOne karam = 1.67 meter
One inch = 2.54 centimeterOne Marla = 272.72 square feet
One furlong = 600 ftOne Marla = 25.10 square meter
One foot = 0.36 varsOne kanal = 20 Marla
One furlong = 40 rodsOne kanal = 502 square meter
One mile = 8 furlongOne kanal = 180 square karam
One mile = 320 rodsOne acre = 160 square rods
One mile = 800 linksOne acre = 160 poles
One mile = 80 chainsOne acre = 0.4047 hectare
One mile = 320 perchesOne Acre = 100 square meter
One mile = 5280 ftOne link = 7.92 inches
One perch = One poleOne link = 0.66 foot
One perch = One rodOne link = 0.20 meter
One perch = 16.5 ftOne N = 0.101 kg
One rod = One perchOne kg = 9.8 N
One perch =25 linksOne ounce = 0.062 lb
One kg = 2.204 lbOne kg = 1000 gram
One ton = 1000 kgOne gram = 0.001 kg

Unit Conversation

  1. One foot = 12 inches
  2. One foot = 0.304 meter
  3. One foot = 304.8 mm
  4. One foot = 30 cm
  5. One inch = 25.4 mm
  6. One inch = 2.54 centimeter
  7. One yard = 3 ft
  8. One yard = 36 inches

Slump Value for Different Concrete Work

Concrete Work

Slump Value in the mm

Mass Construction25-50
Beams and Slabs12-25
Cement Concrete Pavement30-75
Deck of Bridge20-30
Vibrated Concrete50-100
Retaining Wall and Column75-150

Slump Value for the different Concrete

What are the basic things a Civil Engineer should know?

BASIC THINGS FOR THE CIVIL ENGINEERS.

1. Lapping in the reinforcement is not allowed for the bars having diameters more than Thirty Six mm.
2. The Steel Char maximum spacing is 1.00 m (or) One No per 1m2.
3. In the steel dowels, a rod minimum of twelve mm diameter should be used.
4. The Steel Chairs minimum of twelve mm diameter bars to be used.
5. Longitudinal reinforcement should not be less than 0.8% and more than Six % of gross C/S.
6. The minimum bars used for a square column are Four No and Six No for the circular column.


Thank You For Reading This Important Information. Get Benefits And Share With New Commers.

Junaid Iqbal.

Civil Engineering Tech.

Civil Engineering Technology is Official Educational and Training Page for Engineering Students. Our Mission is to Educate and Keep People Informed by Creating a Trusted Source of Knowledge Everything Related to Civil Engineering.

Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *

Back to top button